PP-MRP Hot Note - Update of table PPH_PFE_CHANGE
As of SAP Enhancement Package 7 for SAP ERP 6.0 (release 617), a new table was introduced on the standard system to store the planning file entries of the MRP Fiori apps. This table should be updated...
View ArticleCapacity Requirement Table KBED
This post is describing how KBED entries are changed according to the status of production order. Basics Table KBED saves capacity requirement records. Field BEDID is key field of table KBED, and also...
View ArticleStorage Location MRP
The Purpose of this document is to explain the significance of “Storage Location MRP”. This feature gives you flexibility to: 1) Exclude storage location stock from MRP 2) Plan storage location stock...
View ArticleBOM selection logic in MRP
The BOM selection logic is quite complex as several customizations and fields of the material master are involved, so I am summarizing it here. First of all, the BOMs of a material may exist in the...
View ArticleMRP: Planning regularly a specific material
In some situations, we want to have a specific material planned on a regular basis by MRP, even when there was no MRP relevant change for this material and the planning file was not set. This is...
View Article"Shift Order" indicator in customizing Tcode OPU3
"Shift Order" indicator in customizing tcode OPU3 controls if the actual dates of the partially confirmed operations are taken into account during a new scheduling run. Prerequisite Create a production...
View ArticleConvert PIT time used in scheduling to real date - Report CYDATTIM
Scheduling internally converts the dates in seconds relative to a reference date (1980.1.1). It is called PIT time. E.g. 1 o'clock on 1980.1.1, 1 hours is 3600 seconds, so this date/time is represented...
View ArticleDump with error CO889 while creating production orders and a BOM checking tool
A dump below with error CO889 occurs if there are more than 99 phantom materials on one level of BOM when a production order is created. The cause is that the length of the field keeping the number of...
View ArticleMRP execution parameters
There are several parameters below in the initial screen of MRP execution transactions like MD01, here, I am summrizing their usages and also introduce how they work with their corresponding...
View ArticleSubcontracting requirements are not considered in long-term planning
In SAP standard the subcontracting requirements are not considered in the long-term planning.In transaction MS04 the subcontracting dependent requirements are not displayed.You can find further...
View ArticleScheduling Levels for Integrated Long, Mid and Short Term Planning
Sometimes I wonder how much flexibility, great thought and opportunity for business improvement was packed into SAP-ERP. Yes, it's not the new, flashy poster child of SAP, but it has an enormous amount...
View ArticleWhat can I check if MRP does not plan a material?
One of the most frequent issues described on SCN threads is that MRP does not plan a specific material. The idea behind this blog is to describe exactly what can be checked to ensure that all the...
View ArticleIs your system prepared to take advantage of MRP on HANA?
As I have explained on my previous blog MRP on HANA: What's new?, as of SAP Enhancement Package 7 for SAP ERP 6.0, MRP was completely redesigned to take full advantage of the SAP HANA architecture.Now...
View ArticleUseful books for studying Production Planning
I have already seen many threads on this space asking for books to study production planning, therefore, I have decided to share here the books that I consider more relevant on this area. Starting with...
View ArticlePP-CRP Hot Note: Planned orders are not lead time scheduled
You are running MRP on your system with the parameter Scheduling = '2 - lead-time scheduling and capacity planning', as shown on the figure below: After the MRP execution, you are observing the...
View ArticleBAdIs and Exits for production and process orders
As I see daily on the Manufacturing PP space threads asking for exits or BAdis for specific scenarios, I decided to create this list with the most important user-exits and BAdIs that are available for...
View ArticleHow to check why the field content is poped up automatically
You wonder why a field is filled automatically by the system. How to make it happen? Here are some general settings: 1. In the screen levelFirstly find which screen the field belongs to. Take the...
View ArticleAlternate Item group Concept in BOM , SAP PP !
An alternative item group is used to group together alternative items in a BOM. Any of the materials in the alternative item group could be included in the assembly. These items are known as...
View ArticleWork Center cannot be deleted
Very frequently, problems are observed when deleting a work center on transactions such as CR02, CRC2 or IR02. The work center can be deleted directly on the mentioned transactions if we choose the...
View ArticleSerial Number Replacement
If RF ID has scanned wrong Serial number for a FG material, then the procedure to replace it with new serial number is as belowSteps1) Change the production order using CO02 transaction.2) Click on...